A 30-minute weekly construction cost review.
A weekly cost review is a short, fixed meeting where the project manager, finance and a director look at budget against actual for each project, what is approved but unpaid, and what is waiting for approval. Thirty minutes is enough if the figures are ready before the meeting and every gap leaves the room with an owner and a date.
Who attends
- The project manager for each project, or one at a time if you run several.
- Finance, who prepares the figures.
- A director, who makes the decisions nobody else can.
- The quantity surveyor, when quantities or subcontract stages are on the agenda.
Figures to bring
- Budget, spent and approved, by cost item, for each project.
- Approved but unpaid amounts, with due dates.
- Requests waiting for approval, and for how long.
- Cash in hand, and what falls due in the next four weeks.
- Exceptions from the week's reconciliation.
If the figures are not ready before the meeting, the meeting becomes a data-gathering session. Prepare them by the end of the day before.
The 30-minute agenda
| Minutes | Topic |
|---|---|
| 0 to 5 | Actions from last week: done or not, and why |
| 5 to 15 | Budget against actual for each project, starting with cost items over 80% used |
| 15 to 20 | What we owe and the four-week cash view |
| 20 to 25 | Requests waiting, and reconciliation exceptions |
| 25 to 30 | Decisions, owners and dates |
Questions to ask
- Which cost items are using budget faster than the work is progressing?
- What did we commit to this week that is not yet paid?
- Is anything urgent stuck waiting for approval?
- Did any payment happen without a request?
- What will we need to pay in the next four weeks, and can we?
A worked example
The figures below are illustrative.
| Cost item | Budget (KES) | Spent and approved (KES) | Remaining (KES) | Decision |
|---|---|---|---|---|
| Concrete works | 4,200,000 | 2,100,000 | 2,100,000 | On plan. No action |
| Formwork | 900,000 | 840,000 | 60,000 | 93% used with two floors left. QS to re-estimate by Thursday, and the project manager to check reuse of formwork |
| Casual labour | 1,600,000 | 620,000 | 980,000 | On plan. No action |
One item needed attention, and it left the meeting with two owners and a date. That is a good week. For a fuller list of comparisons to bring to the meeting, see how to detect cost leakage early.
What to do with a gap
- Explain it. Sometimes it is timing, such as materials bought early for the next stage.
- Recover it. A supplier credit, a short delivery to chase or rework to charge back.
- Re-forecast it. Update the budget with an approval, so the new figure is a decision.
- Pause it. Stop non-urgent spending on that item until the gap is understood.
- Escalate it. If the client changed the scope, it may be a variation to price and bill.
Running the review in MjengoKit
MjengoKit shows budget against actual by category, cost item, milestone and project, what is waiting for approval and what is approved but unpaid. Figures export to Excel for the meeting pack. See construction budget tracking and construction financial management software.
Bring your last cost report. We will show you the same review in MjengoKit, ready before the meeting.
Book a 20-minute demo