Construction cost control

A 30-minute weekly construction cost review.

By the MjengoKit team. Updated 7 November 2026. 7 min read.

A weekly cost review is a short, fixed meeting where the project manager, finance and a director look at budget against actual for each project, what is approved but unpaid, and what is waiting for approval. Thirty minutes is enough if the figures are ready before the meeting and every gap leaves the room with an owner and a date.

Who attends

  • The project manager for each project, or one at a time if you run several.
  • Finance, who prepares the figures.
  • A director, who makes the decisions nobody else can.
  • The quantity surveyor, when quantities or subcontract stages are on the agenda.

Figures to bring

  • Budget, spent and approved, by cost item, for each project.
  • Approved but unpaid amounts, with due dates.
  • Requests waiting for approval, and for how long.
  • Cash in hand, and what falls due in the next four weeks.
  • Exceptions from the week's reconciliation.

If the figures are not ready before the meeting, the meeting becomes a data-gathering session. Prepare them by the end of the day before.

The 30-minute agenda

Minutes Topic
0 to 5 Actions from last week: done or not, and why
5 to 15 Budget against actual for each project, starting with cost items over 80% used
15 to 20 What we owe and the four-week cash view
20 to 25 Requests waiting, and reconciliation exceptions
25 to 30 Decisions, owners and dates

Questions to ask

  • Which cost items are using budget faster than the work is progressing?
  • What did we commit to this week that is not yet paid?
  • Is anything urgent stuck waiting for approval?
  • Did any payment happen without a request?
  • What will we need to pay in the next four weeks, and can we?

A worked example

The figures below are illustrative.

Cost item Budget (KES) Spent and approved (KES) Remaining (KES) Decision
Concrete works 4,200,000 2,100,000 2,100,000 On plan. No action
Formwork 900,000 840,000 60,000 93% used with two floors left. QS to re-estimate by Thursday, and the project manager to check reuse of formwork
Casual labour 1,600,000 620,000 980,000 On plan. No action

One item needed attention, and it left the meeting with two owners and a date. That is a good week. For a fuller list of comparisons to bring to the meeting, see how to detect cost leakage early.

What to do with a gap

  1. Explain it. Sometimes it is timing, such as materials bought early for the next stage.
  2. Recover it. A supplier credit, a short delivery to chase or rework to charge back.
  3. Re-forecast it. Update the budget with an approval, so the new figure is a decision.
  4. Pause it. Stop non-urgent spending on that item until the gap is understood.
  5. Escalate it. If the client changed the scope, it may be a variation to price and bill.

Running the review in MjengoKit

MjengoKit shows budget against actual by category, cost item, milestone and project, what is waiting for approval and what is approved but unpaid. Figures export to Excel for the meeting pack. See construction budget tracking and construction financial management software.

See it working on your own numbers

Bring your last cost report. We will show you the same review in MjengoKit, ready before the meeting.

Book a 20-minute demo
FAQs

Frequently asked questions

What is a construction cost review?

A regular meeting that compares budget with actual spending on each project, checks commitments and cash, and decides what to do about any gap.

How often should contractors review project costs?

Weekly. Monthly reviews find overruns after the money has gone.

Who should attend the weekly cost review?

The project manager, finance and a director, with the quantity surveyor when quantities or subcontract stages are involved.

What is budget versus actual in construction?

A comparison of what each cost item was budgeted to cost with what has been spent and approved so far, so that overruns show up while there is still time to act.

What should happen after the review?

Every gap should have an owner and a date, and those actions open the next week's meeting.