How to manage multiple construction projects financially.
To manage several projects financially, run every site through the same process, give every shilling a project code, decide in writing how money may move between projects, and review company-wide obligations every week. The danger is rarely one big loss. It is one project quietly funding another until neither can pay its suppliers.
Use one process for every site
When each site has its own habits, one uses a duplicate book, another WhatsApp, a third phones the director, and nothing can be compared. Agree one way of working: the same requisition form, the same cost types, the same approval limits and the same reporting day. Differences between projects should come from the work, not from the paperwork. Differences between sites are also where cost leakage is hardest to spot.
Give every shilling a project
Every request and payment should carry a project code from the start. Shared costs, such as the office, vehicles, plant and supervision, need a rule:
- Allocate by use, such as days a vehicle or machine spent on each site.
- Allocate by size, such as a share of each project's value, for general overheads.
- Keep it as company overhead, and recover it through your pricing.
Choose one rule for each kind of cost and apply it every month. What you must avoid is costs being charged to whichever project still has budget left.
Moving money between projects
It happens: a client pays late on one project, and another project's money covers its payroll. If it happens, make it visible:
- Record it as a transfer between projects, with the amount, the reason and who approved it.
- Agree when it will be paid back, usually when the late client payment arrives.
- Review every open transfer at the weekly meeting.
- Set a ceiling, so that one project cannot drain another.
Check your client contracts as well. Some require project funds to be used only for that project.
Watch company-wide obligations
Each project can look fine on its own while the company runs short of cash. Every week, add up what you owe across all projects and compare it with your cash and the client payments you expect. The four-week plan below is illustrative.
| Week | Opening cash | Client receipts expected | Payroll, suppliers and subcontractors due | Closing cash |
|---|---|---|---|---|
| 1 | 4,600,000 | 0 | 1,840,000 | 2,760,000 |
| 2 | 2,760,000 | 3,500,000 | 2,210,000 | 4,050,000 |
| 3 | 4,050,000 | 0 | 2,960,000 | 1,090,000 |
| 4 | 1,090,000 | 0 | 1,520,000 | -430,000 |
Week 4 runs short. Seen in week 1, that is a conversation with a client about a payment date, or with a supplier about terms. Seen in week 4, it is a payroll you cannot meet.
The Monday review
Spend 30 minutes every Monday on three questions for each project, then one for the company:
- What did we spend last week, against budget?
- What is approved but not yet paid?
- What is waiting for approval?
- Across all projects, can we pay what is due in the next four weeks?
Our guide to a 30-minute weekly cost review gives a full agenda.
Warning signs
- One project is always "borrowing" from the others.
- Suppliers on one site start chasing payment while others are paid on time.
- Payroll is paid late, or in parts.
- Costs move between projects at month end.
- Nobody can say, without a day of work, what the company owes in total.
Managing several projects in MjengoKit
MjengoKit shows each project and all projects together: total spent, approved and budgeted with what remains, spending by category, upcoming payments and outstanding obligations. Every request and payment carries its project. See construction financial management software, and our guide to tracking expenses across sites.
Bring two of your active projects. We will show you both in one view in MjengoKit.
Book a 20-minute demo