How to track outstanding construction payments.
To track what you owe, keep three numbers for every supplier, subcontractor and payroll: what you approved, what you have paid and what is still outstanding. Update them weekly from your approved requests and payments, check them against supplier statements every month, and plan next month's cash from the outstanding total.
The three numbers
- Approved: what you have committed to pay, whether or not an invoice has arrived.
- Paid: what has actually left your accounts.
- Outstanding: approved minus paid. This is what you owe.
Add a due date to each line, and you can see what has to be paid this week. The figures below are illustrative.
| Payee | Approved (KES) | Paid (KES) | Outstanding (KES) | Due |
|---|---|---|---|---|
| Hardware supplier | 200,000 | 142,500 | 57,500 | This week |
| Plumbing subcontract | 1,200,000 | 720,000 | 480,000 | By stage |
| Casual payroll, this week | 386,400 | 0 | 386,400 | Friday |
| Steel supplier | 195,000 | 195,000 | 0 | Paid |
| Total | 923,900 |
Build a weekly payables list
Once a week, after the week's payments, update one list for the whole company:
- Add every request approved during the week.
- Record every payment against the request it settles, including part payments.
- Sort the list by due date, and flag anything overdue.
- Give the list to whoever plans cash, and to the directors.
One list, kept by one person, beats several lists kept on several sites. Our cost leakage guide shows why paid is not the same as spent when you judge a budget.
Check supplier statements every month
Ask your regular suppliers for a monthly statement and compare it with your list. Differences usually mean one of three things: an invoice you have not recorded, a payment the supplier has not allocated, or a credit note one side has missed. Resolve each one, because unresolved differences turn into disputes, and disputes cost you credit terms.
Plan cash from what you owe
Your outstanding list is the starting point for a short cash plan: opening cash, plus client payments you expect, minus what falls due, for each of the next four weeks. When a week looks short, decide early what gets paid first. Payroll and critical suppliers usually come first, and a supplier who hears about a delay before the due date is far more forgiving than one who finds out after.
Common mistakes
- Tracking invoices only. Approved work and orders not yet invoiced are still money you owe.
- Ignoring part payments. A request paid in two parts must show what remains after the first.
- Forgetting retention and deductions withheld from subcontractors, which must still be paid later.
- Separate lists per site that nobody adds up.
Tracking outstanding payments in MjengoKit
MjengoKit records part payments against the request, shows the outstanding balance and blocks payments above it. The dashboard shows upcoming payments and outstanding obligations across projects, and the cash statement shows opening and closing balances. See construction payment software and our payment management guide.