Construction payments

How to reconcile construction project expenses.

By the MjengoKit team. Updated 7 November 2026. 8 min read.

Reconciling construction expenses means matching every line on your M-Pesa and bank statements to a payment record and an approved request, then investigating anything that does not match. Do it weekly, not at month end, so that a missing receipt is a one-week problem and not a one-month mystery.

Why weekly beats monthly

At the end of a week, people still remember why a payment was made, receipts are still in pockets and wrong numbers can still be chased. At the end of a month, the same questions take hours, and some never get answered. A weekly routine also tells you how much cash you really have before you commit to next week's spending.

What you need

  • Statements for every account you pay from: the M-Pesa line, till or paybill, and the bank account.
  • Your payment records: vouchers or the payment list, each with its requisition number.
  • Evidence: invoices, receipts, delivery notes and signed payroll sheets.

The weekly routine, step by step

  1. Export the statements for the week, from the first day to the last.
  2. Tick each outgoing statement line against a payment record.
  3. Tick each payment record against an approved request.
  4. List the exceptions: anything that did not tick on both sides.
  5. Resolve or escalate each exception, with a named owner and a date.
  6. Update the project totals, so budget against actual reflects the real spend.
  7. Sign off: the preparer and a reviewer confirm the week is closed.

How to match statement lines

  • Match on three things: the amount, the date and the recipient. An M-Pesa statement shows the recipient's name and a transaction code for each line.
  • Record the M-Pesa code on every payment record when you pay. It turns matching into a search instead of a guess.
  • Treat transaction charges as their own cost line, so project totals agree with the statement.
  • Watch for split payments: one approved request paid in two parts is two statement lines and one request.

Exceptions and what they usually mean

Exception Usual cause What to do
Statement line with no payment record Paid outside the process, or the record was never entered Find the request and approval. If there is none, escalate
Payment record with no statement line Not yet paid, or paid from another account Check the other accounts, then correct the record
Amounts differ Part payment, charges or a typing error Correct the record and note why
The same payment appears twice Duplicate payment Ask the payee to refund or credit you
Recipient name does not match the payee Wrong number, or something worse Investigate the same day

A worked example: one week of M-Pesa payments

The lines below are illustrative.

Day Paid to Amount (KES) Matched to Result
Monday Hardware supplier, Paybill 142,500 PAY-1192, request REQ-0482 Matched
Tuesday Peter O., mason 9,120 Payroll REQ-0490 Matched
Wednesday An unknown number 15,000 Nothing Exception: the site manager paid a fundi directly. A request and approval are raised now, and the rule is restated
Thursday Fuel station, till 12,000 PAY-1189 Matched
Thursday Hardware supplier, Paybill 142,500 PAY-1192 again Exception: paid twice. The supplier credits the next invoice

Two exceptions in one week is normal at the start. What matters is that both were found within days, not discovered at the end of the project. For the other comparisons that catch leaks early, see how to detect cost leakage before it becomes a major loss.

Who does what

Role Task
Finance Prepares the reconciliation and lists exceptions
Project manager Explains exceptions on their projects
Director Reviews the summary and anything unresolved
Accountant Uses the closed weeks for the monthly accounts

The person who made the payments should not be the only person who reconciles them.

Reconciling in MjengoKit

In MjengoKit, each payment sits on the request it settles, with its reference. The cash statement shows money in and out with opening and closing balances, and a request can be marked as paid if it was settled another way. Statements export to Excel for your accountant. See construction payment software, or start with our free expense tracker.

See it working on your own numbers

Bring last week's M-Pesa statement. We will show you how each line would match in MjengoKit.

Book a 20-minute demo
FAQs

Frequently asked questions

How often should a contractor reconcile expenses?

Weekly. Monthly reconciliations leave too long between a payment and the question about it, and cash decisions are made on figures that may be wrong.

How do I reconcile an M-Pesa statement?

Download the statement for the week, match each line by amount, date and recipient to a payment record that carries the M-Pesa code, and investigate anything left over.

What should I do with M-Pesa transaction charges?

Record them as their own cost line, so that your project totals agree with the statement.

What if a payment has no receipt?

Find the request and approval, and ask the payee for a receipt or invoice. Keep it on the exceptions list until it is resolved. If it keeps happening, change the rule.

Is reconciliation the accountant's job?

Finance prepares it and project managers explain the exceptions. The accountant relies on the result at month end.