How to manage subcontractor payments in Kenya.
Manage subcontractor payments by agreeing the scope, price and payment stages before work starts, paying each stage only after someone has checked the work and approved the request, and keeping a running total of what has been paid and what remains. That running total is what prevents overpayment and most disputes.
Agree the basics in writing
Before work starts, write down:
- The scope of work, specific enough that both sides can tell when it is finished.
- The price, and what it includes, such as materials, labour and transport.
- The payment stages, each tied to a milestone you can check on site.
- Any advance, and how it will be recovered.
- Retention, if your contract uses it: a share of each payment held back until the work is complete and defects are fixed.
- How variations are priced and approved before extra work starts.
A simple payment schedule
Tie each payment to work you can see. This example for a KES 1.2 million plumbing subcontract is illustrative.
| Stage | Milestone | Share | Amount (KES) |
|---|---|---|---|
| Mobilisation | Start of works | 20% | 240,000 |
| First fix | Ground floor complete | 20% | 240,000 |
| First fix | First floor complete | 20% | 240,000 |
| Second fix | All floors | 25% | 300,000 |
| Testing and handover | Pressure test passed | 15% | 180,000 |
| Total | 100% | 1,200,000 |
Advances: pay them, then recover them
Many subcontractors need money to mobilise. If you pay an advance, agree how it comes back. A common approach is to deduct a fixed share from each later stage until the advance is recovered, so that the final payment is not left to carry it all. Record the advance as a payment against the subcontract, not as a loose transfer.
Approve each payment against work done
Before each payment, someone who did not negotiate the subcontract should check the work: a site engineer or quantity surveyor, with photos or measurements where useful. If a stage is only partly complete, pay for the part that is done, or agree a date to come back. Then the payment request goes for approval like any other spending.
Keep a running total
For every subcontract, keep one line per payment showing what it was for, who approved it, what was paid and what remains. The figures below continue the illustrative example.
| Payment | Linked to | Approved by | Paid (KES) | Remaining (KES) |
|---|---|---|---|---|
| Mobilisation | Start of works | Director | 240,000 | 960,000 |
| First fix | Ground floor | QS, then director | 240,000 | 720,000 |
| First fix | First floor | QS, then director | 240,000 | 480,000 |
The running total answers the question every director eventually asks: how much have we paid them, and how much is left? Our guide to subcontractor cost leakage lists the warning signs to watch for.
Withholding tax and invoices
Some payments to subcontractors can attract withholding tax under Kenya's income tax law. Where it applies, you deduct it from the payment and remit it to KRA. KRA's withholding tax guide explains which payments are covered and the current rates. Agree with your accountant which of your subcontract payments it applies to, and record any deduction against the payment it came from.
Ask each subcontractor for an electronic tax invoice. KRA says business expenses must be supported by an electronic tax invoice, as at 1 January 2024, for them to be deductible.
Handling disputes
Most disputes are about whether a stage is finished, or about extra work. Both are easier to settle with records: the agreed scope, measurements and photos, the approval history and the payment history. Raise concerns as soon as you see them, pay the part of a stage that is not in dispute if your contract allows it, and agree variations in writing before the extra work starts.
Doing this in MjengoKit
In MjengoKit, each subcontract has a scope of work or deliverable. Payment requests go through approval, can link to a project milestone, and are paid by M-Pesa or bank using saved details. Each subcontract shows what has been paid and what remains. See subcontractor management software, and our construction payment management guide for the wider payment process.