Construction procurement

How to control material purchasing on construction sites.

By the MjengoKit team. Updated 7 November 2026. 8 min read.

Material purchasing is under control when every order can be traced to an estimate, an approved request, a quote and an LPO, and when someone regularly compares what was bought with what the work should need. The six steps below work with a notebook, a spreadsheet or software.

Step 1: Estimate before you buy

Work out the quantities each stage needs before the first order: from the drawings, the bill of quantities if you have one, or your own take-off. Break the estimate down by milestone, such as foundations, ground floor slab and walling, so that each request can be checked against the stage it is for.

Step 2: Request and approve

Every material purchase starts as a requisition with the item, unit, quantity, rate, stage and date needed. The approver checks the quantity against the estimate and the price against recent quotes before agreeing. Our free requisition form has all of these fields.

Step 3: Compare quotes for larger purchases

For large or unusual orders, ask two or three suppliers to quote. Compare more than the unit price:

  • delivery to your site, and how soon;
  • credit terms, and what happens if you pay late;
  • the specification, such as cement grade or steel diameter;
  • the supplier's record on short deliveries and quality.

Record the quotes on the request, so the approver can see what was compared. The cheapest quote is not always the best buy.

Step 4: Order with an LPO

Once a request is approved, send the supplier an LPO stating the items, quantities, rates, delivery site and date. If different suppliers will deliver different items, split the order into separate LPOs. Our guide to LPOs, requisitions and invoices shows what an LPO should contain.

Step 5: Check deliveries against the LPO

Count or measure what arrives, check it against the LPO, and sign the delivery note only for what you received. Note any shortfall or damage on the note itself. Then pay only for what was delivered, which is the simplest protection against paying for goods that never arrived.

Step 6: Compare purchases with the estimate

Once a week, compare what each stage was estimated to need with what has been requested and bought so far. The example below is illustrative.

Item Estimate for this stage Already requested New request What to do
Cement 600 bags 520 bags 200 bags Ask why the total would reach 720 bags
Y12 steel 4 tonnes 2.5 tonnes 1 tonne Within the estimate, so approve
Ballast 60 tonnes 36 tonnes 20 tonnes Within the estimate, so approve

A request above the estimate is not automatically wrong. Wastage, rework or a design change may explain it. The point is that someone asks before the money is spent, not after.

Warning signs to look out for

  • Requests that regularly exceed the estimate, from the same site or person.
  • Repeated small orders of the same item, just under an approval limit.
  • One supplier who always wins, at prices above other quotes.
  • Deliveries to a different site from the one on the LPO.
  • Surplus materials left at the end of a stage, while new orders continue.

For the physical side of protecting materials once they are on site, see how to prevent material theft. For every other way money leaks out of a project, see construction cost leakage: 10 ways your project is losing money.

Where MjengoKit fits

MjengoKit controls the money side of materials: requests by project and cost item, approvals, LPOs sent on WhatsApp, payments, and budget against actual for materials. It does not count stock on site, so keep your delivery notes and store records alongside it. See construction material tracking and construction procurement software.

See it working on your own numbers

Bring one recent material order. We will show you how it would look from request to payment in MjengoKit.

Book a 20-minute demo
FAQs

Frequently asked questions

What is construction material procurement?

The process of buying materials for a project: estimating what is needed, requesting and approving purchases, comparing quotes, ordering with an LPO, receiving deliveries and paying suppliers.

How many quotes should I get for materials?

Two or three for large or unusual purchases. For routine items from a trusted supplier, check the price against the market regularly rather than quoting every order.

How do I stop over-ordering materials?

Estimate each stage before buying, ask for the stage on every request, and have the approver compare the request with what has already been bought for that stage.

Should the site or the office buy materials?

Either can. What matters is that the site requests, someone else approves, and payment is made only against an approved order and a signed delivery note.

Does MjengoKit track stock on site?

No. MjengoKit tracks requests, approvals, orders and payments for materials. Keep delivery notes and a store record for the physical stock.

Book a 20-minute demo and discover your spending confidence.

Bring one recent material order. We will show you how it would look from request to payment in MjengoKit.