How to manage construction purchase approvals.

By the MjengoKit team. Updated 7 November 2026. 7 min read.

A good construction approval process gives every request one clear path: the right person checks it against the budget, approves or rejects it with a reason, and nobody pays until that is done. Use amount limits so routine requests clear quickly and directors only see the large or unusual ones.

What an approval is for

An approval is not a signature for the file. It is a short check that answers five questions:

  1. Is this needed now, for this project?
  2. Is it in the budget, and how much of that budget line is left?
  3. Is the quantity reasonable for the work?
  4. Is the price fair, and were quotes compared for larger buys?
  5. Is the supplier, subcontractor or worker the right one to pay?

If an approver cannot answer these from the request, the request is incomplete, and it should go back to the site. Approval is where procurement leakage, such as split purchases and unchecked prices, is easiest to stop.

Who approves what

Different kinds of spending need different checks. One way a mid-sized contractor might split the work is shown below. The roles are illustrative.

Request Checked by Approved by Paid by
Materials Site engineer, against the estimate Project manager, then director above the limit Finance
Casual labour payroll Site engineer, against attendance Project manager Finance
Subcontractor payment Quantity surveyor, against work done Director Finance
Site overheads Site manager Project manager or finance manager Finance

How many levels, and what limits?

Most contractors need one level for small amounts and two for larger ones. A third level is worth it only for very large or unusual items. Every extra level adds delay, and delay is what pushes site teams around the process.

Amount (illustrative) Level 1 Level 2 Target time
Under KES 50,000 Project manager Not needed Same day
KES 50,000 to 500,000 Project manager Finance manager Within 24 hours
Over KES 500,000 Project manager Director Within 48 hours

Speed versus control

A slow approval process does not create control. It creates workarounds. Keep approvals fast by:

  • letting approvers decide from a phone, not only at the office;
  • naming a deputy when an approver travels;
  • setting a target time for each level, and checking it;
  • sending incomplete requests back with a clear reason instead of leaving them unanswered.

Approve or reject, always with a reason

A rejection without a reason teaches the site nothing, and the same request comes back next week. Write what is wrong: the quantity exceeds the estimate, the price is above the last quote, or the budget line is nearly used. Keep comments on the record, so that anyone looking later can see why a decision was made.

Handling urgent purchases

Allow a capped emergency route: a named person approves by phone, the approval is confirmed in writing the same day, and a requisition follows within 24 hours. Review every emergency at the weekly cost meeting. Our guide on preventing unauthorised spending includes a sample policy.

Red flags in an approval process

  • Rubber-stamping: every request approved within seconds, none ever rejected.
  • Request splitting: several requests for the same item from the same site within days, each just under a limit.
  • Self-approval: people approving their own requests, or an assistant approving for a manager.
  • Approval after payment: requests approved once the money has already gone.

Approvals in MjengoKit

MjengoKit routes each requisition to the approvers set for that approval type, level by level. Approvers work from an "awaiting my approval" queue on a phone or laptop, can comment, and must give a reason to reject. Every decision is kept in the approval history, and roles decide who can make payments. See construction approval workflow software.

See it working on your own numbers

Tell us your approval rules. We will show you how they run in MjengoKit, level by level.

Book a 20-minute demo
FAQs

Frequently asked questions

What is a construction approval process?

The rules that decide who must agree before project money is committed, at what amounts, and what they must check before they agree.

How many approval levels should a contractor have?

Usually one level for small amounts and two for larger ones. Add a third only for very large or unusual purchases, because every level adds delay.

What is request splitting, and how do I spot it?

Breaking one purchase into several smaller requests to stay under an approval limit. Look for repeated requests for the same item from the same site within a few days, each just below a limit.

Can approvers approve from their phones?

In most systems, yes. In MjengoKit, approvers work from a queue of items awaiting their approval on a phone or a laptop.

Should finance approve purchase requests?

Finance should check budget availability and payment details. The person who pays should not be the only person who approved the request.